PITTSFIELD, Mass. — Be advised that the city's street improvement work continues with the following schedule in place for Oct. 18 to Oct. 23.
-
Oct. 18: Lowering structures on Crane Avenue from Oak Hill Road moving west, approximately 2000 feet, towards 553 Crane Avenue.
-
Oct. 21: Milling Crane Avenue (same section as above)
-
Oct. 22: Paving of Crane Avenue (same section as above)
-
Oct. 23: Curb installation on Crane Avenue (same section as above)
On-street parking is prohibited during this work between the hours of 6 a.m. to 6 p.m.